Fabriek Shell Pernis krijgt nieuwe kolom
02 dec. 2019
Vernieuwing vindt niet alleen plaats tijdens een grote onderhoudsstop. Heel het jaar door controleert en vernieuwt Shell Pernis onderdelen aan de fabrieken.
Onlangs werd op een van de fabrieken een nieuwe kolom geïnstalleerd. Benieuwd hoe deze spectaculaire klus is uitgevoerd? Kijk dan naar de video.
Nieuwe kolom Shell Pernis
Title: REPLACEMENT OF COLUMN C3201 AT SHELL PERNIS
Duration: 02:00 minutes
Description:
Video about the the Girbotols factory at Shell Pernis getting a column C3201 replacement.
Replacement_of_Column_C3201_at_Shell_Pernis_Transcript
[Music plays]
Swelling adventurous music
[Video footage]
Aerial shot of Shell Pernis with the smokestacks, pipes and silos.
[Text displays]
REPLACEMENT OF COLUMN C3201
AT SHELL PERNIS
[Video footage]
Wide panning shot from left to right of installation of pipes at Shell Pernis RTA department with two workers in PPE looking up. Steady wide shot of smokestacks surrounded by scaffolding. Steady medium shot of a worker in PPE climbing up the ladder of a smokestack. Point of view shot from the upper scaffolding looking over to the river next to the Pernis complex. Medium shot of workers in PPE on top of Column C3201 discussing and working.
[Music]
Music fades to background
[Voice of Roy Lagers, Leader Shell Pernis]
We are here at Shell Pernis at the RTA department. We are standing in the Girbotols factory. Here we remove the sulphur components from the propylene and propane flows of the Catcracker.
[Video footage]
Medium shot of Roy Lagers in PPE talking to the interviewer.
[Text displays]
ROY LAGERS
Project Leader Shell Pernis
[Roy Lagers, Leader Shell Pernis]
To put it in other words: by de-sulfurizing these products we prevent our sandwich bags smelling like rotten eggs.
[Video footage]
Over shoulder medium shot of two workers in PPE looking at two other workers in PPE doing a maintenance check. Medium shot of the two discussing workers, pointing at the site being checked. Medium shot of one of the workers going down the column to inspect.
[Voice of Roy lagers]
At the beginning of this year, during a major maintenance, we found out that the column C3201...
[Video footage]
Medium shot of Roy Lagers in PPE talking to the interviewer.
[Roy Lagers]
...was really outdated and needed to be replaced.
[Video footage]
Wide shot of a crane near the column c3201 lifting a pipe. Medium shot of a worker in PPE measuring the width of the column. Close up of the worker writing the measurements on a notebook tilting towards his face.
[Voice of Roy lagers]
So we set up a project, which we executed in the past week,
[Video footage]
Medium shot of Roy Lagers in PPE talking to the interviewer.
[Roy Lagers]
where we replaced the old column with a brand new one; C3201.
[Video footage]
Wide time lapse at daytime of two cranes lifting the old column out of place.
[Voice of Rob van Dijk, Block Leader]
A very special part of the process is the lifting.
[Video footage]
Medium shot of Rob van Dijk in PPE talking to the interviewer.
[Text displays]
ROB VAN DIJK
Block Leader
[Rob van Dijk]
We are dealing with enormous weights in a running factory, with big cranes
and a lot of transport movements. That really requires thorough preparation.
[Music]
Music swells and fades to background when Rob starts speaking.
[Video footage]
Wide time lapse in early morning with 2 cranes lifting and manoeuvring the brand new column into place.
[Voice Rob van Dijk]
The challenges in this project were mainly to get the job completed
in this very compact area,
[Video footage]
Medium shot of Rob van Dijk in PPE talking to the interviewer.
[Rob van Dijk]
at multiple heights, with very diverse activities,
[Video footage]
Wide time lapse in the early morning of a worker watching the brand new column being lifted and directed to the right place.
[Voice of Rob van Dijk]
with safety as a number one priority and...
[Video footage]
Medium shot of Rob van Dijk in PPE talking to the interviewer.
[Rob van Dijk]
...to eventually deliver a high quality end result.
[Video footage]
Wide time lapse of the column being put into place.
[Voice of Roy Lagers]
What makes this project so special
[Video footage]
Medium shot of Rot Lagers in PPE talking to the interviewer.
[Roy Lagers]
is that we’ve very recently, actually in April to be exact, made the decision to replace this column.
[Video footage]
Wide time lapse of the column being put into place.
[Voice of a Roy Lagers]
This meant that, between April and November, something that would normally take 24 months to do,
[Video footage]
Medium shot of Rot Lagers in PPE talking to the interviewer. Wide shot looking up to two workers in PPE standing on scaffolding. Medium shot of three workers standing on ground level of the complex discussing. Wide shot looking up to workers walking down the stairs of a column.
[Voice of Roy Lagers]
That's really a remarkable achievement for a big team. A lot of people were involved.
[Video footage]
Medium shot of Rot Lagers in PPE talking to the interviewer.
[Roy Lagers]
That's something I am very proud of.
[Video footage]
Medium upwards tilt from the foot of a column to the top. Shot of smokestacks surrounded by scaffolding. Aerial shot of Pernis from that we started with.
[Music]
Music swells before it fades out.
[Video footage]
Shell logo appears on white screen.
[Text displays]
Subscribe for more
© Shell International 2019